# Channel Infrastructure lifts Marsden Point 2050 fuel throughput forecast by 1.3 billion litres as diesel and petrol demand persists

> Envisory's long-term modelling finds slower vehicle replacement and gradual electric vehicle adoption will sustain transport fuel demand, adding 300 million litres in 2050 while Channel estimates the Government's strategic diesel reserve costs 1 cent per litre.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Markets, Telecommunications & National Grid
- **Kicker:** NZX CONTINUOUS DISCLOSURE · MARSDEN POINT INFRASTRUCTURE · FUEL SECURITY
- **Byline:** NZX Limited (Channel Infrastructure NZ Limited)
- **Published UTC:** 2026-11-02T00:00:00+13:00
- **Canonical URL:** https://civicrecord.nz/article/channel-infrastructure-envisory-fuel-throughput-outlook-2026/

---

## Key Figures

- **Cumulative throughput uplift to 2050:** +1.3 billion litres — Increase compared to Envisory's October 2024 long-term forecast
- **2050 base case annual uplift:** ~300 million litres — Additional annual petrol and diesel throughput in 2050
- **Strategic diesel reserve insurance cost:** ~1 cent / litre — Estimated holding and tank cost for full nine days of reserve cover
- **Diesel stockholding requirement:** 21 days (28 by July 2028) — Mandatory minimum stockholding obligation under national fuel security rules

Channel Infrastructure NZ Limited has released an updated long-term fuel throughput forecast for Marsden Point prepared by energy consultancy Envisory, projecting an additional 1.3 billion litres of cumulative fuel demand through to 2050 compared to its October 2024 forecast.

The revised outlook concludes that domestic demand for petrol and diesel will remain higher for longer than previously projected. Softer macroeconomic conditions have extended commercial and private vehicle replacement cycles, while the gradual pace of electric vehicle fleet penetration will take longer to displace liquid fuels. Envisory's base case models an extra 300 million litres of annual petrol and diesel throughput in 2050.

Envisory also expects Channel Infrastructure's share of national fuel delivery to expand, underpinned by population growth across Auckland and the scale efficiency of the Marsden Point import terminal and pipeline network. Near-term jet fuel projections were moderated to reflect revised passenger forecasts and high aviation fuel pricing in 2026, though long-haul international travel demand remains steady.

Chief Executive Rob Buchanan highlighted that persistent diesel demand underscores the strategic significance of New Zealand's fuel resilience arrangements. The Government established a nine-day strategic diesel reserve this year, utilizing Marsden Point storage tanks under a contract running to December 2027, which Channel calculates provides national economic insurance at an equivalent cost of approximately 1 cent per litre.

New Zealand currently enforces a minimum stockholding obligation of 21 days for diesel, which is scheduled to lift to 28 days in July 2028, alongside a 24-day jet fuel obligation. Channel confirmed its FY26 guidance remains unchanged, assuming 2 percent growth in jet fuel volumes.

> "Envisory’s outlook for total fuel throughput to 2050 is 1.3 billion litres higher than its previous forecast, and of particular note is that diesel demand is predicted to remain higher over a longer timeframe."
> — **Rob Buchanan**, Chief Executive, Channel Infrastructure NZ Limited

## Primary Sources

- **NZX Limited (New Zealand Exchange — Market Announcements)** (27 Oct 2026): Channel releases updated Envisory fuel demand outlook — [Original Document](https://www.nzx.com/announcements/482360)