Napier City Council delivers $23.5m in first-quarter capital works against $116.3m budget and delegates new Resource Management Act powers

The council’s delivery committee has reviewed first-quarter capital spending across urban infrastructure and water services while formally transferring new planning powers to officers under Resource Management Act transitional rules.

$23.5m
Capital Delivered
Delivered as at 30 September 2026
$116.3m
Amended Budget
Covers Urban Infrastructure and Water Services
$17.2m
Urban Infrastructure
Includes $38.6m Te Kete project allocation
$6.3m
Water Services
Carry forwards and rephasing finalised in amended budget

Napier City Council delivered $23.5 million in capital works during the first quarter of the 2026/27 financial year, representing a 20 per cent expenditure against its amended annual capital budget of $116.3 million, according to performance reporting tabled before the Delivery and Regulatory Performance Committee.

The council's capital programme is divided between Urban Infrastructure, which delivered $17.2 million against an amended allocation of $87.8 million, and Water Services, which completed $6.3 million against a budget of $28.5 million. Delivery managers confirmed that a targeted capital programme reprioritisation exercise is nearing completion to adjust upcoming project phasing, while expressing confidence that full-year urban infrastructure expenditure will exceed the previous year's record of $63 million.

Major project allocations for the year include $38.6 million for the Te Kete project, $5.4 million for the NCC Animal Shelter, $4.8 million for the Emerson Street Project, and $3.8 million for transport renewals. Inter-council bridge projects with Hastings District Council, including Brookfields Bridge at $1.9 million and Redclyffe Bridge at $1.2 million, are currently phased with initial spending predominantly funded by the New Zealand Transport Agency and Hastings, with Napier's financial share scheduled to expand during subsequent construction stages. An additional 28 projects valued at $21 million have been allocated through the Urban Infrastructure Panel.

Alongside capital reporting, the committee formally approved updated non-financial delegations to align council operations with Resource Management Act transitional provisions. Under the approved framework, Strategy and Policy managers received statutory authority under section 76A of the Act to remove or amend defunct matters from the Napier District Plan, while planning officers were granted authority under section 104AA to determine that specified land-use activities may proceed as permitted activities during the transition period.