# Electricity Authority proposes removing South Island Winter Energy Margin and updating grid reliability benchmarks from 2028

> The Electricity Authority Te Mana Hiko is consulting on changes to the methodology and assumptions behind New Zealand's security of supply standards in Part 7 of the Electricity Industry Participation Code 2010, with submissions closing at 5pm on Tuesday 17 November 2026. The proposals would remove the separate South Island Winter Energy Margin, model new peak-capacity investment as grid-scale batteries rather than thermal plant, and bring contingent hydro storage into dry-year modelling.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Business, Energy & Primary Sector
- **Kicker:** ELECTRICITY AUTHORITY · SECURITY OF SUPPLY
- **Byline:** Energy & Regulation Desk
- **Published UTC:** 2026-11-16T15:18:05.985Z
- **Canonical URL:** https://civicrecord.nz/article/ea-security-of-supply-standards-review/

---

## Key Figures

- **Preliminary base-case WCM:** 488 MW — Optimal Winter Capacity Margin excluding reserves, an effective increase of ~374 MW due to separate reserve treatment
- **Intermittent pipeline share:** 83% — Proportion of projects in New Zealand's generation investment pipeline classed as intermittent wind or solar generation
- **Current national energy standard:** 14–16% — Existing New Zealand Winter Energy Margin in Part 7 of the Code, alongside a 25.5–30% SI-WEM and 630–780 MW WCM

The Electricity Authority Te Mana Hiko is seeking submissions by 5pm on Tuesday 17 November 2026 on proposed changes to how New Zealand's electricity security of supply standards are calculated under Part 7 of the Electricity Industry Participation Code 2010 and the supporting Security Standards Assumptions Document (SSAD). Established in 2012 and last reviewed without amendment in 2018, the current Code benchmarks set a New Zealand Winter Energy Margin (NZ-WEM) of 14 to 16 per cent, a South Island Winter Energy Margin (SI-WEM) of 25.5 to 30 per cent, and a Winter Capacity Margin (WCM) of 630 to 780 MW to guide the System Operator's annual Security of Supply Assessment (SOSA) over a one-to-10-year horizon.

The Authority says the power system has changed materially since 2018: 83 per cent of projects in New Zealand's generation pipeline are intermittent generation, grid-scale batteries are emerging as flexible capacity, thermal plant increasingly operates as firming or reserve capacity amid more uncertain domestic gas availability, and electrification and large new loads are making demand harder to forecast. The Authority notes the review is also timely given the Government's proposed Winter Energy Reliability Obligation (WERO), which, if implemented, could give the security standards and SOSA a greater role in informing future market-participant obligations to manage dry-year risk.

For winter peak capacity, the Authority proposes modelling additional capacity investment as battery energy storage systems (BESS) rather than thermal generation, introducing an updated shortage cost curve, and continuing to separate reserve requirements from the WCM so the margin reflects surplus generating capacity after reserves are met. Preliminary base-case modelling indicates an optimal WCM of 488 MW (with a base-case system cost of $196 million), compared with the current value of 690 MW—a figure the Authority notes represents an effective increase of approximately 374 MW once the different treatment of reserve requirements is accounted for.

For dry-year energy adequacy under the NZ-WEM, the Authority proposes incorporating contingent hydro storage at Lake Hāwea (67 GWh), Lake Tekapo (220 GWh), and Lake Pūkaki (545 GWh in total, including 331 GWh accessible to Meridian Energy under normal conditions for the next three years following a recent fast-track consent decision and 214 GWh tied to an Official Conservation Campaign), while applying a penalty cost tested at sensitivities of $0/MWh, $200/MWh, and $800/MWh so the model draws on contingent water only after lower-cost options are exhausted. The base case also assumes Huntly unit 5 and any new dry-year reserve generation run on liquefied natural gas (LNG), though terminal and supply-chain infrastructure costs are excluded because funding and cost-recovery arrangements for LNG import infrastructure are not yet known. In addition, the Authority proposes updating the WEM shortage cost curve for consumer price inflation since 2018 and testing the May 2024 20-year Tiwai Point aluminium smelter demand-response contract—approximately equivalent to 2.5 per cent of mid-winter demand—as a sensitivity rather than in the base case.

The Authority proposes removing the separate SI-WEM from the Code and SSAD from the 2028 SOSA, concluding that upgraded HVDC transfer capability—currently an 850 MW steady-state southward operating limit—and forecast South Island renewable generation make a South Island energy shortage highly unlikely without the NZ-WEM first signalling a national issue. Ahead of the full Code change consultation planned for early 2027 and intended implementation from the 2028 SOSA, the Authority expects to decide by the end of 2026 on interim SSAD updates requiring clearer System Operator assumptions on generation pipeline project classification and demand forecasting for the 2027 SOSA.

## Primary Sources

- **Electricity Authority (Te Mana Hiko)** (17 Nov 2026): Review of security of supply standards — [Original Document](https://www.ea.govt.nz/documents/10990/Review_of_Security_of_Supply_Standards_Consultation_Paper.pdf)