# Hawke’s Bay Regional Council reports main construction set to begin on North Clyde floodway, centrepiece of $70 million Wairoa flood project protecting 586 properties, while possible river mouth groyne remains unfunded

> With main construction expected to be complete in late 2027, the 1.1km-long floodway will provide North Clyde’s 586 Category 2C properties with protection from a 1 per cent annual exceedance probability flood.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Environment, Transport & Regions
- **Kicker:** FLOOD PROTECTION
- **Byline:** The Civic Record
- **Published UTC:** 2026-11-18T02:23:40.425Z
- **Canonical URL:** https://civicrecord.nz/article/hbrc-wairoa-north-clyde-floodway-main-construction/

---

## Key Figures

- **Project funding:** $70 million — Crown-funded Wairoa Flood Mitigation Project
- **Properties covered:** 586 — North Clyde Category 2C properties protected to 1% AEP standard
- **Floodway scale:** 1.1km × 190m — Main construction expected to be complete in late 2027

Main construction on the North Clyde floodway—the centrepiece of the $70 million Crown-funded Wairoa Flood Mitigation Project—is officially set to begin following a morning karakia held at Takitimu Marae on 18 November 2026, Hawke’s Bay Regional Council reports. Once complete, the 1.1km-long, 190m-wide floodway will provide the 586 North Clyde properties that received Category 2C classifications after Cyclone Gabrielle with protection from a 1 per cent annual exceedance probability flood, defined as a flood with a 1 per cent chance of occurring in any given year.

Goodman Contractors, appointed through an Early Contractor Involvement process led by Hawke’s Bay Regional Council with a focus on local contractors and supply chains, have been on site since early 2026. Initial tree clearing was followed from August by a wider enabling works programme comprising demolition, site establishment, and a temporary haul road between Waihirere Road and Ruataniwha Road built across whenua made available by Tātau Tātau o Te Wairoa.

The first stage of main construction will focus on the town side stopbank area alongside project-related stormwater and drainage works, with main construction expected to be complete in late 2027. Cultural monitors from local marae will be on site throughout, and all contractors will complete a cultural, archaeological, ecological, and environmental induction this week. Hawke’s Bay Regional Council stated that residents can expect more trucks, machinery, and signage around North Clyde as main construction gets underway, and that the project team will let people know ahead of any works likely to affect them directly.

Crown Manager Lawrence Yule acknowledged the whānau still living under Category 2C classifications, the landowners and whānau who made decisions regarding their homes, land, and whenua so the wider community could be protected, and the guidance of mana whenua including Takitimu, Ruataniwha, and Tawhiti a Maru Marae and Tātau Tātau o Te Wairoa. Hawke’s Bay Regional Council Chair Sophie Siers said Wairoa had waited nearly forty years for protection since Cyclone Bola showed the town’s vulnerability to flooding, while Wairoa Mayor Craig Little said seeing machinery on the ground and the floodway taking shape gave people "something real to hold on to" after living with uncertainty and rain anxiety.

While Hawke’s Bay Regional Council describes the project as the largest infrastructure investment Wairoa has seen in decades, parts of the wider whole-of-catchment approach to flood resilience remain in progress or unfunded. Mr Yule said upper-catchment modelling is due by the end of the year, while investigations are continuing into a possible river mouth training groyne—a separate workstream that is not yet funded.

> "More than three and a half years after Cyclone Gabrielle, we’re now building the protection this community has been waiting for."
> — **Lawrence Yule**, Crown Manager