AOTEAROA NEW ZEALAND · JOURNAL OF PUBLIC RECORD

The Civic Record

National Affairs, Parliament, the Courts, Energy, Markets & Local Government

MERCURY NZ · RENEWABLE GENERATION

Mercury breaks ground on $506m Puke Kapo Hau wind farm after issuing Notice to Proceed under Fast-track approvals

Mercury has begun construction on its $506 million Puke Kapo Hau development west of Dunedin, adding 40 turbines to the Mahinerangi site to create New Zealand's largest wind farm with 228MW total installed capacity.

$506m
Capital Investment
Funded on balance sheet
192MW
Added Capacity
40 new turbines (52 total)
648GWh
Annual Generation
Powers equivalent of 92,000 homes
200 workers
Peak Construction
Two-year delivery schedule

Mercury NZ Limited has formally commenced civil construction on the $506 million Puke Kapo Hau wind farm west of Dunedin, marking the start of physical works after issuing Notice to Proceed for what will become New Zealand's largest operating wind generation asset.

The development forms Stage 2 of the Mahinerangi Wind Farm, which was originally commissioned in 2011 with 12 turbines. Puke Kapo Hau will erect 40 new turbines delivering 192MW of additional capacity. Once fully commissioned following a two-year construction programme, Stages 1 and 2 combined will comprise 52 turbines with 228MW of total installed capacity, producing approximately 648GWh of renewable electricity annually—sufficient to power the equivalent of 92,000 households.

The project represents Mercury's first renewable build consented under the Fast-track Approvals Act, and will be the first wind farm constructed under the legislation. The Mercury Board approved the project in August, and the Notice to Proceed followed the completion of grid connection studies with Transpower.Works will be funded directly from the company's balance sheet within established corporate financial guardrails.

A formal groundbreaking ceremony was held on site with Mercury Chief Executive Stew Hamilton, Clutha Mayor Jock Martin, and Te Rūnanga o Ōtākou Ūpoko Edward Ellison. Civil delivery will be carried out alongside primary contracting partners Higgins, Electronet, and German turbine manufacturer Nordex, with the project supporting up to 200 workers daily during peak construction. Mercury also confirmed the establishment of an annual community fund to support surrounding Otago communities.

“We have delivered five of the six wind farms constructed in New Zealand over the past five years, demonstrating our ability to execute major renewable energy projects safely, on time and on budget.”

Stew Hamilton — Chief Executive, Mercury NZ Limited