Napier City Council delivered $89 million in capital works during the year ended 30 June 2026—the largest annual capital programme in the city’s history—while recording an unaudited operating deficit of $16.6 million against a budgeted surplus of $6.7 million, according to Risk and Assurance Committee minutes published ahead of Council’s formal adoption meeting on 22 October.
Financial Controller Charles Witty and Senior Advisor Corporate Planning Jane McLoughlin reported to the committee—attended by Ernst & Young Appointed Auditor David Borrie—that the operating variance was driven primarily by total revenue falling $20.6 million below budget and expenditure sitting $2.7 million above budget. Consequently, operating revenue covered 87 percent of operating expenditure, below the statutory balanced-budget benchmark.
Officers noted, however, that core controllable operating costs including employee remuneration and maintenance expenditure finished below budget. The revenue shortfall reflected lower New Zealand Transport Agency (NZTA) co-funding, reduced financial contributions, lower investment property revaluation gains, and softer user charges, while the expenditure variance stemmed from higher non-cash depreciation and amortisation on newly commissioned infrastructure assets.
Net council borrowings closed the financial year at $109 million—$21 million below budget due to capital project rephasing—leaving Napier with approximately $225 million in available borrowing capacity. Across non-financial targets, the council achieved or substantially achieved 107 of its 138 performance measures (78 percent).