NZ TRANSPORT AGENCY · COROMANDEL RESILIENCE

NZTA updates Coromandel resilience programme for SH25, SH26 and SH2, targeting March–July 2027 works at priority sites

Backed by $20 million for State Highway 25 and $65 million for State Highway 26 at Kōpū from Budget 2026 alongside a longer-term Crown resilience programme, NZTA intends to progress work at two SH25 bridges and nine Crown-funded sites between March and July 2027, subject to detailed design at the bridges.

$20 million
SH25 resilience funding
Budget 2026 funding for targeted resilience improvements on State Highway 25
$65 million
SH26 Kōpū funding
Budget 2026 funding to replace SH26 Kirikiri Stream Bridge and upgrade the SH26-SH25A intersection
9 sites
Crown-funded sites
Targeted for delivery between March and July 2027, including SH25 Thames Coast Road and SH2 Karangahake Gorge

NZ Transport Agency Waka Kotahi (NZTA) is progressing a resilience programme across two funding streams—Budget 2026 and longer-term Crown resilience funding—to better protect vulnerable sections of Coromandel state highways from slips, rockfall, erosion, and drainage failures during severe weather. Budget 2026 included $20 million for targeted resilience improvements on State Highway 25 (SH25) and $65 million to replace the SH26 Kirikiri Stream Bridge at Kōpū and upgrade the nearby SH26-SH25A intersection.

Under the $20 million SH25 programme, NZTA intends to progress work at Manaia River Bridge and Owera Bridge between March and July 2027, subject to detailed design being completed. Four further locations have been identified at Whenuakite, Waikawau, Te Kouma Hill, and Whangapoua Hill, with up to five additional sites currently being prioritised for work staged over the next four years.

Alongside this, NZTA intends to deliver work at nine sites between March and July 2027 through the Crown-funded resilience programme, including underslip and rockfall protection on SH25 Thames Coast Road between Ruamahunga and Tapu and near Whakatete and Kereta, as well as underslip treatment on SH2 in the Karangahake Gorge near Waikino. NZTA Regional Manager, Infrastructure Development & Delivery, Roger Brady said work planned for this summer will be timed to avoid the busiest holiday periods although some disruption will be unavoidable, noted that the programme sits alongside recovery work following the January storms, bridge replacements at Tairua and Ramarama, and ongoing maintenance, and cautioned that the improvements cannot remove every risk or prevent all future disruption; individual project timings and traffic management details remain to be provided before work starts.

“Maintaining reliable access around the Coromandel is particularly important for communities, businesses and visitors. Work planned for this summer will be timed to avoid the busiest holiday periods, although some disruption will be unavoidable”

Roger Brady — Regional Manager, Infrastructure Development & Delivery, NZ Transport Agency Waka Kotahi