# NZTA reports one-year progress on SH2 Hawke’s Bay Expressway and prepares for summer start on Pākōwhai Interchange pending contractor appointment

> Early site preparation has begun at the Pākōwhai and Links Road roundabout for the final major package of the approximately 7.5-kilometre four-laning upgrade between Napier and Hastings, after crews installed all bridge beams across three expressway bridges during the first year of works.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Environment, Transport & Regions
- **Kicker:** STATE HIGHWAYS
- **Byline:** The Civic Record
- **Published UTC:** 2026-11-22T23:24:55.898Z
- **Canonical URL:** https://civicrecord.nz/article/nzta-reports-hawkes-bay-expressway-pakowhai-interchange-start/

---

## Key Figures

- **Four-laning corridor:** Approx. 7.5 km — Upgraded State Highway 2 route between Taradale Road and south of Pākōwhai Road
- **Daily traffic volume:** Around 29,000 — Vehicles per day using the route between Napier and Hastings
- **Tūtaekurī River Bridge:** 276 m — All 44 Super-T beams installed on the new two-lane structure, built 1.2 metres higher than the existing bridge
- **First-year site works:** Around 10,000 m³ — Concrete poured alongside more than 150,000 mahi hours completed since November 2025

NZ Transport Agency Waka Kotahi reports that early preparation works are underway at the Pākōwhai and Links Road roundabout ahead of main construction planned for this summer on the new Pākōwhai Interchange, the final major package of the State Highway 2 Hawke’s Bay Expressway Road of National Significance project. A contractor has yet to be appointed for the interchange package; Regional Manager of Infrastructure Development and Delivery Rob Partridge said the agency will finalise the construction approach and traffic management arrangements once that appointment is made.

The new interchange will replace the existing roundabout at the intersection of Pākōwhai Road and Links Road, carrying four lanes of State Highway 2 overhead with roundabouts beneath the expressway and new northbound and southbound on- and off-ramps connecting to local roads. The package also includes around two kilometres of four-laning, extending the four-lane alignment being built from the north through the interchange and across the Tūtaekurī-Waimate Stream before joining the existing two-lane highway to the south.

Across its full extent between Taradale Road and south of Pākōwhai Road, the wider expressway project will deliver approximately 7.5 kilometres of four-laning on a corridor between Napier and Hastings that carries around 29,000 vehicles each day and links Hawke’s Bay Airport, Napier Port, and the regional hospital.

Preparations at Pākōwhai coincide with the one-year mark since main expressway construction began in November 2025 at the Tūtaekurī River Bridge. All 44 Super-T beams are now installed on the new 276-metre bridge, which will carry two additional lanes across the river and sits 1.2 metres higher than the existing bridge to improve resilience against future floods and earthquakes. Foundations and bridge beams are also complete at the new Meeanee Road and Kennedy Road overbridges, where crews are building the bridge structures, approaches, and associated roadworks.

Traffic is already running on part of the new northbound alignment between Kennedy Road and Taradale Road while work continues on the median, remaining lanes, and four-laning south of Taradale Road. During the first year of construction, crews poured around 10,000 cubic metres of concrete and completed more than 150,000 mahi hours on site. NZTA will hold public information sessions on the project at the Hawke’s Bay Farmers’ Market in Waipatu, Hastings, from 8.30am to 12.30pm on Sunday 29 November, and at Taradale Library in Napier from 3pm to 6pm on Tuesday 1 December.

> "Once a contractor is appointed, we can finalise the construction approach and traffic management arrangements ahead of main works getting underway."
> — **Rob Partridge**, Regional Manager of Infrastructure Development and Delivery, NZ Transport Agency Waka Kotahi