AOTEAROA NEW ZEALAND · JOURNAL OF PUBLIC RECORD

The Civic Record

National Affairs, Parliament, the Courts, Energy, Markets & Local Government

NZ TRANSPORT AGENCY WAKA KOTAHI · STATE HIGHWAY 2

NZTA reopens two-lane traffic through Waioweka Gorge under 50 km/h limit after installing 45-metre rockfall attenuator

Two-way travel past the Goldsmith and Snake Gully slip sites restores vital freight and community capacity between Bay of Plenty and Tairāwhiti following severe January storms, ahead of final pre-Christmas resurfacing.

~45 metres'.
Attenuator Span
High-tensile steel rockfall mesh
>10 m³
Debris Captured
Captured shortly after installation
50 km/h
Temporary Speed Limit
Pending pre-Christmas paving
April 2027
Resilience Works Start
Wider gorge stability programme

NZ Transport Agency Waka Kotahi (NZTA) has restored two-lane traffic on State Highway 2 through the Waioweka Gorge, reopening both directions past the critical Goldsmith and Snake Gully slip sites under a temporary 50 km/h speed limit following an on-site safety inspection.

The reopening marks a primary recovery milestone for the inter-regional freight and travel corridor linking Bay of Plenty and Tairāwhiti, which was shut in both directions for more than three weeks after severe weather triggered extensive slips in January 2026. Ongoing recovery operations have combined slope stabilisation, loose rock scaling, ground investigations, and specialist structural protection.

At the Goldsmith slip site, contractors installed a custom-designed rockfall attenuator spanning approximately 45 metres across the cliff face. Constructed from high-tensile steel mesh, cables, and energy-absorbing components designed to decelerate falling debris, the attenuator successfully captured more than 10 cubic metres of rockfall shortly after being commissioned.

NZTA Bay of Plenty Area Manager (Asset and Operations) Sandra King confirmed that pavement upgrades are scheduled for completion ahead of the Christmas holiday break to restore permanent speed limits through the slip sections, subject to weather conditions. The agency acknowledged civil contractors Higgins, Waiotahi, Geovert, Beca, and Stellar Projects, alongside local hapū Ngāti Ira, while noting that several other gorge locations remain under single-lane traffic management.

Beyond immediate slip repairs, NZTA is currently evaluating multiple locations across the Waioweka Gorge for wider resilience, with the programme expected to be finalised in the coming months and work expected to begin by April 2027.

“This is the result of months of intensive work, from ground investigations, removal of loose rock and slope stabilisation, and specialist construction.”

Sandra King — Bay of Plenty Area Manager, Asset and Operations, NZ Transport Agency Waka Kotahi