# NZTA schedules 5.5-kilometre Transmission Gully pavement reconstruction following premature surface deterioration

> Transport agency overhauls motorway drainage and lays heavy structural asphalt between Paekākāriki and SH58, funding works from the 2024 confidential project settlement.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Infrastructure, Transport & Climate
- **Kicker:** NZ TRANSPORT AGENCY WAKA KOTAHI · STATE HIGHWAY 1 TRANSMISSION GULLY · PAVEMENT RECONSTRUCTION
- **Byline:** NZ Transport Agency Waka Kotahi
- **Published UTC:** 2026-11-03T00:00:00+13:00
- **Canonical URL:** https://civicrecord.nz/article/nzta-transmission-gully-summer-pavement-reconstruction-2026/

---

## Key Figures

- **Pavement reconstruction:** 5.5 kilometres — Structural asphalt rebuilding on SH1 Transmission Gully
- **Drainage improvements:** 4.5 kilometres — Subsurface drainage installation to halt water ingress and cracking
- **Hutt Valley resurfacing:** 13.8 lane km — Resurfacing on SH2 from Ngauranga to Maoribank
- **Funding source:** 2024 settlement — Reserved from confidential Transmission Gully dispute restructuring

NZ Transport Agency Waka Kotahi has confirmed a major summer maintenance programme for State Highway 1 Transmission Gully (Te Aranui o Te Rangihaeata), initiating 5.5 kilometres of pavement reconstruction and 4.5 kilometres of drainage improvements after road surfaces deteriorated earlier than expected.

Water entering the motorway pavement has accelerated surface cracking and potholing across key sections. Rather than applying seasonal chipseal, road crews will rebuild the underlying foundation using heavy structural asphalt to deliver long-term pavement durability.

Wellington Alliance Manager Roxanne Hilliard said works will occur in two stages: drainage installations in southbound lanes between Paekākāriki and the State Highway 58 interchange starting 8 November and concluding by 18 December, followed by full asphalt reconstruction from 12 January through to March.

Funding for the repairs has been drawn directly from reserves established under the confidential 2024 settlement and restructuring of the Transmission Gully public-private partnership contracts, avoiding additional capital allocations.

Alongside the motorway works, NZTA announced that contractors will resurface 13.8 lane kilometres of State Highway 2 through the Hutt Valley between Ngauranga and Maoribank over five weeks of night operations, managing high-volume corridors carrying more than 34,000 vehicles daily.

> "Drainage improvements will help protect the reconstructed pavement from water, while the pavement work will replace the priority sections with stronger structural asphalt."
> — **Roxanne Hilliard**, Wellington Alliance Manager, NZTA

## Primary Sources

- **NZ Transport Agency Waka Kotahi** (29 Oct 2026): Targeted summer maintenance programme on the way for State Highway 1 Transmission Gully/Te Aranui o Te Rangihaeata — [Original Document](https://www.nzta.govt.nz/media-releases/targeted-summer-maintenance-programme-on-the-way-for-state-highway-1-transmission-gully)
- **NZ Transport Agency Waka Kotahi** (23 Oct 2026): State highway summer maintenance programme – State Highway 2 Hutt Valley works planned — [Original Document](https://www.nzta.govt.nz/media-releases/state-highway-summer-maintenance-programme-state-highway-2-hutt-valley-works-planned)