TAURANGA CITY COUNCIL · LANDFILLS & GROWTH FUNDING

Tauranga staff outline Te Maunga and Cambridge Park closed-landfill works and advise against broad city centre development contribution cuts

A supplementary agenda for Tauranga City Council's 19 November 2026 Long Term Plan workshop sets out a $13.5 million Te Maunga programme and an unconfirmed $12.63 million Cambridge Park estimate under Regional Council abatement notices, while recommending a review of student-accommodation contribution rates rather than sweeping city centre charge reductions.

$13.5m
Te Maunga programme
Closure and reconsenting option; highest-cost capping concept revised down to $7.80m
$12.63m
Cambridge Park estimate
Draft FY28–FY32 capital estimate (unconfirmed) ahead of 31 May 2030 consent expiry
$37,404
Citywide residential DC
Excl. GST per three-bedroom dwelling, plus $9,345 excl. GST in Te Papa Infill North
~$15.9m
Growth Fund estimate
Illustrative 10-year central government grant (~$1.6m/yr) for ~9,346 forecast dwellings

Tauranga City Council staff have tabled capital programmes for the closed Te Maunga and Cambridge Park landfills ahead of a Long Term Plan (LTP) workshop at 10:00 am on Thursday, 19 November 2026, warning that delaying investment to renew ageing infrastructure risks further Regional Council enforcement action, environmental harm to nearby streams and wetlands, and higher future costs. At Te Maunga—where waste disposal operated from the 1960s to 1995 and a replacement Resource Management Act 1991 consent application was lodged in October 2024—the Regional Council issued an abatement notice in August 2025 requiring the leachate collection system to function properly while Council and Ngā Pōtiki progress a collaborative Best Practicable Option (BPO) process. Capping concepts are being reassessed because revised early rough-order-of-magnitude estimates place the highest-cost cap at $7.80 million, down from a 2024 assumption of $15 million to $30 million, while the overall Te Maunga closure and reconsenting option is listed at $13.5 million.

At Cambridge Park—a legacy, non-engineered closed landfill within a public reserve containing an active BMX track, where disposal ended in 1998—works earlier in 2026 responded to an abatement notice for unauthorised leachate discharge into a stream, with further work planned this year. Existing 1995 discharge consents expire on 31 May 2030, and staff target selecting a long-term leachate treatment pathway by June 2029 and lodging a replacement consent application by December 2029 under an unconfirmed draft capital estimate of $12.63 million across FY28–FY32. Both landfill programmes are set for inclusion in the draft LTP scheduled to go to Council on 15 December 2026.

In a separate supplementary briefing paper on city centre housing incentives, staff examine whether Development Contributions Policy (DCP) settings in Te Papa North and the city centre act as a barrier to residential and mixed-use development ahead of proposed central government reforms to replace development contributions (DCs) with standardised development levies from approximately 2029–30. Currently, citywide DCs total $37,404 excluding GST for a standard three-bedroom dwelling alongside $9,345 excluding GST in Te Papa Infill North local charges—together typically representing around 3 per cent to 5 per cent of total development costs. Staff advise against lowering the cost of capital component (41 per cent of the Te Papa North local charge), altering non-residential scaling factors, reallocating Cameron Road Stage 1 and 2 costs (which would trim Te Papa North local transport DCs by approximately $2,300 per unit while increasing Te Papa South), or shifting citywide residential charges from bedrooms to floor area, concluding those options would largely transfer costs to ratepayers or other growth areas rather than reduce total infrastructure costs.

Instead, staff recommend further investigating student accommodation demand factors—noting Tauranga currently charges 0.4 household unit equivalents per room compared with Auckland Council's 0.22, while a recent special assessment using actual data from a comparable large-scale development found student accommodation generated 65 per cent of standard household water demand and received a 35 per cent DC discount. Staff also outline wider intensification incentives and disincentives—including a dedicated city centre housing incentives fund, development investment, or differential rates on vacant land and empty premises—and note that under the Government's announced $400 million Incentives for Growth Fund (with payments expected from 1 April 2027, potentially subject to the 2026 general election results), Tauranga's forecast growth of approximately 9,346 occupied dwellings between 2023 and 2033 could equate to roughly $15.9 million over 10 years, though those funds cannot be used for water infrastructure or DC-recoverable costs. Consented dwellings in Tauranga rose from 500 in 2024 and 437 in 2025 to 637 in 2026, with attached dwellings climbing from 21 per cent to 32 per cent of consents.