Heritage New Zealand completes 18-month seismic base-isolation retrofit of Turnbull House ahead of mid-2027 reopening

Engineers and contractors have transferred the weight of the more than 100-year-old brick house-library onto a new 500mm-thick concrete raft slab and ten 2.5-tonne base isolators, unlocking the isolators as work shifts to interior restoration.

10 units
Base isolators installed
Each weighing 2.5 tonnes, positioned beneath a new 500mm-thick concrete raft slab
2 metres
Excavated undercroft
Subfloor height excavated beneath the existing brick walls under temporary propping
Mid-2027
Target reopening
Following interior fitouts, heritage reinstatement, services modernisation, and accessibility works

Heritage New Zealand Pouhere Taonga reports that Turnbull House is now officially base isolated, completing an 18-month structural retrofit delivered by the Turnbull House Project team formed in 2019 from a seismic strengthening scheme first conceived in 2017.

Working beneath the existing brick house-library, the project excavated a two-metre-high undercroft, with Naylor Love and Dunning Thornton sequencing the work so that temporary propping put back stability whenever ground was removed. A new subfloor with pads and plinths was then built, and a scaffolded monorail system was used to manoeuvre ten 2.5-tonne base isolators—hung sideways—through narrow doorframes and hallways. A 500mm-thick concrete raft slab was poured above the isolators, hydraulic jacking pre-settled the ground beneath each unit, and the bottom of the existing brick walls was grouted to the slab before temporary props were cut to transfer the building's weight off its more than 100-year-old wall footings and the locking plates were removed.

After more than 18 months focused primarily on seismic strengthening and weathertightness, the project team has turned to interior fitouts, heritage reinstatement, services modernisation, accessibility improvements, and exterior landscaping ahead of a planned mid-2027 reopening.